【End】Internal Test for deepin routine updates in February 15th 2017
Official Announcements 1800 views · 1 replies ·
jingle
deepin
2017-02-15 18:56
Author
Hi everyone, This regular test covers the kernel version 4.9.8 and X Server related contents. We started this regular test to ensure the stability of system. All internal test group members should take an active part in this test. Thank you!
Testing Schedule
2017.02.15: Commence testing
2017.02.15—2017.02.22: Test and fill out the questionnaire for internal testing
2017.02.22: End testing
Test Procedure
Connect to internal source and upgrade the system to the latest edition.
Test according to the questionnaire and fill out the results.
Testing Schedule
Test Procedure
Attention
Acknowledgments
Many thanks to all the Internal Testing Team members for your active participation!